Effective with contracts let on or after February 20, 2025, New York State Department of Transportation (“NYSDOT”) changed Standard Specification Section 102-12. You no longer have a five-day period to submit your utilization plan. These changes will appear in the specifications published May 1, 2025.
Here are the changes you need to pay attention to:
Failure to comply with the changes and submit a complete bid package at the time of bid may deem your bid non-responsive.
This will be a change for both the DBE firms and the bidders. As a contractor, NYSDOT expects you to begin solicitation as soon as the contract is let/advertised for bid. DBEs are expected to provide quotes to the primes as early as possible in order for contractors to review quotes, obtain confirmation, and submit the DBE commitments/confirmation with the bid. NYSDOT has advised that it will not consider any additional information after letting.
Starting May 1, 2025, these same procedures will be implemented for all Local let contracts.
In completing the NYSDOT forms, bidders should note the following:
Additional articles will address the material supplier/trucking categories and how to count.
If you have any questions about registration, please reach out to Lorraine D’Angelo, LDA Compliance Consulting, Inc. by email, lorraine@ldacomplianceconsulting.com or telephone, (914) 548-6369.